After leaving Aqua he move to Protechnical which lead him to work on jobs like Heathrow and The Olympic Village plus many more

Heathrow temporary terminal 2

Our job here was to pre-commission flush the heating and chilled water systems for the temporary arrivals and departures pier erected while the new terminal 2 is built.

London Heathrow Terminal 2

London Athletes Village

Along with many other companies all working together to complete on time for the olympics in 2012 we were part of the team involved in flushing three of the accommodation blocks at the athletes village Block N15 consisted of flushing the heating systems for over 300 apartments, we were also involved in block N9 and N10 consisting of another 200 apartments. Chlorinations were also done at all 3 sites.